Nashville Electric Service said communication was its biggest failure in a Wednesday board meeting while addressing the utility's response to January's ice storm, which left hundreds of thousands of customers without power at its peak.
The February 9 board meeting
The NES board met on Monday, February 9, 2026, according to a FOX 17 report. Board Chair Anne Davis said NES “did not live up to the standards Nashville has come to expect from NES.” The same day, Axios reported the board ordered an independent review of the storm response. At the storm's peak, about 230,000 customers were without power, the FOX 17 report says.
NES approved $1 million for the Winter Storm Recovery Fund, which FOX 17 describes as the largest donation to that fund at that point. The utility listed four immediate priorities: strengthening emergency management and leadership, improving communications and outage information including outage map errors, revisiting estimated restoration time practices, and boosting system resiliency through grid hardening and more vegetation management.
NES also announced customer relief. Disconnections and late fees were suspended through June 2026, and unlimited payment arrangements were offered through December 2026, according to the same report.
What has not been confirmed
A board meeting on Wednesday, March 25, 2026, and the statement that communication was NES's biggest failure at that meeting have not been confirmed. The FOX 17 report does not use the phrase “biggest failure.”
Update, Nov. 13: An Axios report dated June 24, 2026, says the independent after-action report on the storm criticized NES's communication with customers in the early stages of the restoration effort.
Storm timeline
According to FOX 17, the storm arrived on January 24, 2026, and full restoration was reached on February 7. About 230,000 customers lost power at the peak. NES said it restored power to 230,000 households in 13 days and estimated storm damage at $110 million to $140 million, the most severe the utility has faced.
The independent after-action review
WSMV reported on the review, a 130-page report prepared by an independent consulting group and presented to the Electric Power Board in June. It found that NES could have restored power two to five days sooner with earlier outside help, and it said requests for linemen were “not made early or broadly enough.” According to the same report coverage, the largest wave of outside crews arrived eight days into restoration, after the worst outages had been repaired. The review made 58 recommendations. It also found an 800-mile tree-trimming backlog at the time of the storm, against a prior four-year cycle covering 4,600 miles of line. NES expects to finish the backlog by the end of June, and the trimming cycle is set to move to three years next year.
Communication and the city's review
The review found that NES gave no estimated restoration times for about the first week. Its outage phone line, text platform and public outage map failed, and some customers were told their power had been restored when it had not. A separate Metro body, Mayor Freddie O'Connell's Winter Storm Response Commission, released an interim report that FOX 17 reported on August 17, 2026. That report described weaknesses in disaster planning and communications, outdated technology and delays in bringing in outside resources. It said NES's early public statements were seen as “defensive and insensitive,” and that the utility's response improved considerably after the first week. The full commission report is due no later than February 23, 2027.
Board and council actions
At its February 9 meeting, the NES board raised the emergency spending limit on preexisting storm contracts from $500,000 to as much as $5 million per transaction, according to board materials. A February 25 board agenda listed a $140 million reimbursement resolution for the January storm. WSMV reported that the Metro Council was set to discuss a resolution expressing a “lack of confidence” in the utility's performance during the storm; the article did not report the outcome.
What remains unconfirmed
The $10 million figure WSMV attributed to the board for outside storm-assistance contracts does not appear in the board materials. No current outage count or post-June fund total has been published.