New Titans Stadium Update Massive Size Upgrades
Here’s your latest update on the brand new Tennessee Titans stadium and there is a lot to unpack.
If you’ve driven by recently, you’ve probably already noticed just how massive the new stadium is compared to the old one. This $2.2 billion project officially broke ground on February 29, 2024 and is expected to be completed by February 2027. After that, a series of opening events are planned from May through August 2027.
The new stadium is bringing major upgrades to the fan experience. Inside, the improvements are significant. The old stadium had just four escalators, while the new one will have 44. Elevators increase from six to 27, along with fully frictionless concessions designed to speed up service.
Fans will also appreciate double the number of restrooms and a much larger team store. The main store is expanding from 4,000 square feet to 11,000 square feet, plus three additional satellite locations throughout the stadium.
Every level will offer 360-degree views, and the entire venue is being built with high-end finishes, not just premium areas like suites. There are also unique design elements honoring Tennessee high school football as well as boys and girls flag football programs.
For players, the upgrades are just as impressive. Football facilities will be 50 percent larger, and the locker room is designed to comfortably accommodate the full team.
One of the biggest construction highlights is the massive roof, measuring approximately 660 feet wide and supported by a steel cable system. Installation is expected later this year.
And for those wondering about the old stadium, it will not be imploded. Instead, it will be carefully dismantled using cranes and heavy equipment.
Stay tuned for more updates, including renderings and a full tour coming soon.
Construction Progress
The roof has been one of the project's biggest milestones. A WSMV report dated August 12, 2026 said the ETFE cable net system was complete and fully installed, and that crews expected the building to be fully enclosed within about two months. The roof cables were lifted in stages through the spring and summer of 2026, with cranes working around all four sides of the building during the July trade coverage.
The project was reported 75 percent complete at the end of March 2026, when about 2,000 workers were on site each day. By then, two of the four construction cranes had been removed as the job moved toward finishing work.
Seating and Early Bookings
Once complete, the stadium is expected to hold about 60,000 seats, according to the WSMV report. Crews had prepared the seat supports across the 200, 300 and 400 levels, and the west end zone on the 100 level was reported ready.
The Titans have started accepting event bookings for the new building. No specific dates for those events have been announced; the May through August 2027 opening sequence is the only published schedule.
The Schedule
The $2.2 billion project broke ground on February 29, 2024. Coverage in March 2026 from The Associated Press said the stadium was on track for a February 2027 completion. Earlier forecasts had called for full enclosure in fall 2026, so the timeline has moved since those first estimates.
Update, Nov. 13: Earlier, the roof was expected to be installed later in 2026. WSMV's August 12, 2026 report says the ETFE cable net was complete and fully installed. No report that the stadium is fully enclosed has been published, and the February 2027 completion target appears unchanged.